Berth-to-berth passage planning
What is being checked
The inspector is checking whether every voyage is appraised, planned, executed and monitored from berth to berth, including pilotage and contingencies, and whether plans, records and interviews demonstrate that the procedure is applied during real voyages rather than completed only as paperwork.
Ready onboard
0/6 completePractice questions
Answer aloud, then open the preparation point.
1What is the operational purpose of berth-to-berth passage planning?
Every voyage is appraised, planned, executed and monitored from berth to berth, including pilotage and contingencies.
2Show how the procedure was applied on the last voyage.
Use the latest voyage to trace appraisal sources, approved route, waypoint checks, UKC, briefings, execution records, deviations and post-voyage corrections.
3Which decision requires the Master's judgement?
The Master sets safe margins, identifies critical points and decides whether new hazards or changed conditions require amendment, delay or abandonment.
4What happens if the planned control becomes invalid?
Pause progression where necessary, establish safe water and position, reassess the affected leg, amend and recheck the route and rebrief the team before continuing.
5How are changes communicated and recorded?
Brief the affected bridge and machinery personnel, amend the controlled plan or record, obtain required approval and retain the reason and revised limits.
Where an observation may arise
Records exist but the bridge team cannot relate them to the actual voyage or operation.
A material change is not reassessed, approved, briefed or recorded.
Pilotage, anchorage, canal or terminal legs are omitted.
A waypoint, turn or cross-track limit is inconsistent with safe water or manoeuvring ability.
Weather, warning, draft or route change is accepted without new checks.
Master's practical note
Inspect the most constrained turn and the plan's escape option. A route line without an abort decision and safe-water logic is not a complete navigational plan.
Equipment boundary and references
Equipment boundary: Passage planning supports but does not remove the Master's responsibility to respond to actual conditions. Pilotage remains part of the berth-to-berth plan.
References
- OCIMF SIRE 2.0 Question Library Part 1, Version 1.0, Question 4.2.1
- SOLAS Chapter V regulation 34
- IMO Resolution A.893(21)
- ICS Bridge Procedures Guide
- IMO Resolution A.960(23)
Last reviewed: 2026-09-11