QUESTION 5.5.6

Control of hazardous energy

Oil, Chemical, LPG, LNGCargo Control Room, Engine Control Room, Interview - Deck Officer, Interview - Engineer Officer

What is being checked

The inspector is checking whether the permit, risk assessment, isolations, competence and supervision create an effective control system for lockout and control of hazardous energy, and whether recent work followed that system.

Ready onboard

0/6 complete

Practice questions

Answer aloud, then open the preparation point.

1What makes this lockout and control of hazardous energy safe to start?

Confirm the approved permit, competent team and physical controls for electrical, mechanical, hydraulic, pneumatic, pressure, thermal, chemical, gravity and automatic-start sources.

2Who can stop or suspend the permit?

Anyone may stop unsafe work. The authorising officer must suspend it if conditions, scope, personnel or simultaneous operations change.

3How are isolations proved?

Identify every energy source, isolate, lock and tag, dissipate stored energy and prove the safe state at the worksite.

4What change requires reassessment?

A change in scope, atmosphere, weather, equipment status, personnel, nearby operations or validity period requires suspension and review.

5Show that the last job was properly restored.

Trace permit closure to removal of tools and personnel, guard replacement, isolation removal, testing and operational handover.

Where an observation may arise

GENERIC ASSESSMENT

The risk assessment did not address electrical, mechanical, hydraulic, pneumatic, pressure, thermal, chemical, gravity and automatic-start sources.

SITE CONFLICT

Physical inspection did not confirm isolations are individually identified, locked and tagged, stored energy is dissipated and zero energy is proved.

ISOLATION GAP

An energy source, stored pressure, gravity, temperature or automatic start was not isolated and proved safe.

PERMIT ERROR

The permit was expired, pre-signed, issued away from the worksite or inconsistent with the actual job.

SIMULTANEOUS WORK

A conflicting operation or permit was not identified and controlled.

POOR RESTORATION

The job was closed despite residual pressure, suspended load, shared isolation error, missing lock or premature de-isolation.

Master's practical note

Audit one completed permit backwards from equipment restoration to initial isolation. Most weaknesses appear at scope change, shift handover or return to service rather than on the front page.

Equipment boundary and references

Equipment boundary: The permit is an administrative control and does not replace physical isolation, competent supervision or continuous reassessment at the worksite.

References

  • OCIMF SIRE 2.0 Question Library Part 1, Version 1.0, Question 5.5.6
  • ISM Code sections 7 and 10
  • OCIMF Energy Isolation guidance

Last reviewed: 2026-09-13