Electrical-power failure emergency response
What is being checked
The inspector is checking whether the emergency plan, crew competence, equipment readiness and recent drills demonstrate a coordinated response to failure of main electrical power, including realistic decisions rather than a paper exercise.
Ready onboard
0/6 completePractice questions
Answer aloud, then open the preparation point.
1What are your first actions for failure of main electrical power?
Raise the correct alarm, establish command and then explain the immediate priorities: emergency generator start, emergency switchboard supply, steering and navigation loads, communications, machinery restart sequence and blackout prevention.
2Who assumes command if the designated person is unavailable?
Identify the deputy from the muster list or emergency plan and explain how command transfer is communicated.
3Which equipment must be immediately available?
Identify, locate and explain the readiness checks for emergency generator, batteries, emergency lighting, communications and black-start procedures.
4Show what was learned from the last relevant drill.
Use blackout drill, emergency-generator tests and electrical logs to trace one finding through responsibility, correction and verification.
5How are shore and external parties contacted?
Use the scenario-specific contact list and reporting sequence, distinguishing immediate distress or emergency calls from company notification.
Where an observation may arise
The emergency plan did not adequately address emergency generator start, emergency switchboard supply, steering and navigation loads, communications, machinery restart sequence and blackout prevention.
Crew members could not explain their alarm, muster, communication or deputy responsibilities.
Required equipment was inaccessible, defective or not prepared: emergency generator, batteries, emergency lighting, communications and black-start procedures.
The record showed attendance but no credible equipment use, decision-making or scenario development.
Times, participants or results could not be reconciled with blackout drill, emergency-generator tests and electrical logs.
Repeated deficiencies remained open or were closed without testing the corrective action.
Master's practical note
Select one recent drill and ask three different ranks to continue the scenario from an unplanned complication. Consistent actions are stronger evidence than a polished drill report.
Equipment boundary and references
Equipment boundary: Apply the statutory and company drill frequency and scope relevant to the vessel, equipment and trade. Do not operate equipment during an interview where doing so would create risk.
References
- OCIMF SIRE 2.0 Question Library Part 1, Version 1.0, Question 5.1.11
- SOLAS Chapter II-1 regulations 42 and 43
- ISM Code section 8