ECDIS familiarisation and evidence
Applicability: Applies where ECDIS is fitted.
What is being checked
The Master and navigation officers are familiar with the installed ECDIS before independent watchkeeping.
Ready on board
0 / 5 checkedUse the vessel’s actual documents, records and arrangements. Checklist points are drawn from RISQ 3.2.
Practice questions
DeepDraft preparation prompts based on this RISQ entry, not an official inspector interview script.
1Is a separate type-specific approved ECDIS training certificate mandatory under this guidance?
No. The source distinguishes generic approved training from familiarisation with the installed equipment. Objective familiarisation evidence and competence are required; it does not impose a separate type-specific approved-training certificate.
2When must familiarisation be completed?
Before taking an independent navigation watch, each time the deck officer joins a vessel. The SMS should define and document its evaluation.
Where a finding may arise
Missing objective evidence, familiarisation incomplete before independent watchkeeping, or inability to use the installed ECDIS competently may prevent a satisfactory answer. Absence of a separate type-specific approved-training certificate alone is not the requirement stated here.
Past observations for practice
Anonymised reports, manually reviewed before publication. These are reported experiences, not additional inspection requirements.
No reviewed observations have been added for this entry.
Share an observation for private review
Remove vessel, company and inspector names, report numbers, exact dates and confidential information. Do not paste a complete inspection report.
References and source status
RightShip Inspection Ship Questionnaire, November 2025, version 3.2. Section 2, page 24, reference 2.14.
The explanation, checklist and practice answer derive from the supplied questionnaire. Reported observations are separately contributed and manually reviewed; they are not official RISQ guidance.
Independent DeepDraft preparation guide, based on the supplied RISQ 3.2 questionnaire. Not an official RightShip product or inspection report.