Emergency machinery-space bilge pumping arrangements
What is being checked
The inspector is checking whether machinery-space bilges can be pumped promptly during flooding, with emergency suction and overboard controls accessible, marked, protected against misuse and understood by engineer officers.
Ready onboard
0/7 completePractice questions
Answer aloud, then open the preparation point.
1Trace the emergency bilge-suction route from the bilge to overboard.
Use the approved drawing to identify the selected pump, direct suction, discharge valve and operating sequence.
2Who may authorise breaking an overboard-valve seal?
Follow the company authority and emergency procedure, record the reason and seal identity, and notify the Master and shore management as required.
3When can an oily mixture be discharged during flooding?
Only within the MARPOL exceptions necessary for ship safety, saving life or resulting from damage, with all reasonable precautions and full records.
4How do you prevent accidental opening of the emergency overboard valve?
Use clear warnings, controlled access, seals or locks and the ship-specific operating procedure.
5What evidence shows the arrangement remains operable?
Show inspections, permitted functional tests, valve condition, seal records and defect closure without creating an unauthorised discharge.
Where an observation may arise
No ship-specific flooding response or emergency bilge-pumping sequence is available.
An engineer cannot identify the pumps, valves, sequence or MARPOL limitations.
The emergency suction or control is obstructed or not readily accessible.
Valves are unmarked or lack warning against accidental opening.
Required seals are absent, inconsistent with the register or previously broken without record.
A pump, valve or remote control needed for emergency pumping is defective.
Master's practical note
Have the engineer trace the arrangement physically while using the drawing. The critical check is whether the selected pump and every valve can still be reached and operated when the normal bilge arrangement is overwhelmed.
Equipment boundary and references
Equipment boundary: Do not open an emergency overboard path for demonstration. Verification should use drawings, markings, seals, maintenance evidence and an approved safe test method.
References
- OCIMF SIRE 2.0 Question Library Part 1, Version 1.0, Question 6.5.1
- SOLAS Chapter II-1
- MARPOL Annex I
- IMO MSC.1/Circ.1424
Last reviewed: 2026-09-08