Bunker pipeline inspection and pressure testing
What is being checked
The inspector is checking whether the complete HFO and MDO bunker pipeline system is inspected, liquid-pressure tested at the required intervals and maintained with traceable results.
Ready onboard
0/7 completePractice questions
Answer aloud, then open the preparation point.
1Define the complete bunker-system boundary included in the pressure test.
Trace both fuel grades from each manifold through piping and valves to the receiving tanks, including safety and shutdown devices required by the procedure.
2What were the pressure and date of the latest annual test?
Show 100 percent MAWP, liquid test medium, calibrated gauge, hold period, inspection result and approval within the last 12 months.
3When were the two most recent 150 percent MAWP tests completed?
Demonstrate two tests within five years with no interval exceeding three years, or the operator's stricter approved requirement.
4Why must compressed air or inert gas not be used for this pressure test?
A liquid test limits stored energy and follows the specified test basis; pneumatic testing introduces a different and potentially severe rupture hazard.
5How was the test liquid disposed of after completion?
Trace the liquid to an approved tank, treatment route or reception facility and show the associated record.
Where an observation may arise
The test boundary, method, pressure or frequency is undefined.
The annual or higher-pressure test is overdue.
Air or inert gas was used instead of a suitable liquid.
The test gauge is unsuitable or lacks valid calibration.
The latest test date and pressure are not marked on the system.
A pipeline, valve, alarm, relief device, gauge or ESD component in the bunker system is defective.
Master's practical note
Confirm the stated MAWP before accepting any pressure figure. Then reconcile the procedure, calibrated gauge range, test record and physical pipeline marking; the same number should not be assumed for every section.
Equipment boundary and references
Equipment boundary: Test pressure must come from approved design data and company procedure. Never infer MAWP from a previous test marking or conduct pneumatic testing as a substitute.
References
- OCIMF SIRE 2.0 Question Library Part 1, Version 1.0, Question 6.2.3
- MARPOL Annex I
- ISGOTT, current edition
- Approved bunker pipeline drawings and test procedure