Maritime analysis. Real-time insight.

QUESTION 5.4.7

Immersion suits

Oil, Chemical, LPG, LNGBridge, Forecastle, Lifeboat deck

What is being checked

The inspector is checking whether the complete arrangement for immersion suits is within service limits and capable of safe immediate use, and whether officers and assigned crew understand its actual operation.

Ready onboard

0/6 complete

Practice questions

Answer aloud, then open the preparation point.

1How is immersion suits prepared for immediate use?

Follow the posted sequence and include rapid donning, air expulsion, hood and glove positioning, water entry and use with a lifejacket where required.

2What must be checked before release or deployment?

Verify quantity, size, location, bag, zip, face seal, gloves, light, whistle, inflation if fitted and leak or air-pressure test status, personnel position, communications and the area into which the equipment will move.

3Show the maintenance and examination status.

Match physical identification to monthly inspections, periodic air-pressure tests and repair records.

4Who may maintain or adjust the release arrangement?

Follow SOLAS, flag and MSC.402(96) authorisation requirements. Crew routine maintenance does not permit unauthorised overhaul or adjustment.

5What is the alternative if normal deployment is unsafe?

Use the vessel-specific contingency and risk assessment without improvising an unapproved release or lifting method.

Where an observation may arise

CONDITION DEFECT

Inspection identified damaged zip or seal, wrong size, missing light, overdue test, poor stowage or inability to don.

SERVICE GAP

Required evidence was overdue, incomplete or did not match the equipment: monthly inspections, periodic air-pressure tests and repair records.

UNSAFE SECURING

A pin, lashing, obstruction or unauthorised arrangement could prevent immediate deployment.

INSTRUCTION CONFLICT

Posted instructions or crew explanation did not match the fitted system.

KNOWLEDGE GAP

Assigned personnel could not explain rapid donning, air expulsion, hood and glove positioning, water entry and use with a lifejacket where required.

UNCONTROLLED REPAIR

Release, launching or pressure equipment had been adjusted or repaired without required authorisation.

Master's practical note

Check one complete deployment chain from stowage to recovery. A serviced component does not prove that access, power, communication and crew actions will work together.

Equipment boundary and references

Equipment boundary: Operational demonstrations must follow safe drill controls and maker instructions. Do not launch, release or load-test equipment solely to satisfy an interview.

References

  • OCIMF SIRE 2.0 Question Library Part 1, Version 1.0, Question 5.4.7
  • SOLAS Chapter III regulation 7
  • IMO MSC/Circ.1114

Last reviewed: 2026-09-13