QUESTION 5.10.1

Pilot boarding arrangements

Oil, Chemical, LPG, LNGInterview - Deck Rating, Main Deck

What is being checked

The inspector is checking whether planning, equipment condition, competent supervision and real-time monitoring provide safe pilot embarkation and disembarkation under the vessel's actual freeboard, weather, movement and terminal conditions.

Ready onboard

0/6 complete

Practice questions

Answer aloud, then open the preparation point.

1Who authorises and supervises pilot embarkation and disembarkation?

Identify the responsible officer and the competent operator or attendant, including who monitors changing conditions.

2What are the stop criteria?

Use defined limits for pilot-ladder length, combination arrangement, ship-side doors, lee, speed, freeboard, rigging, supervision and communications, equipment defect, lost communication and unsafe movement.

3Show the pre-use inspection.

Physically verify certified pilot ladder, spreaders, steps, side ropes, shackles, strong points, stanchions, lighting, lifebuoy and heaving line and reconcile the check with pilot-ladder inspection log, certificate, rigging checklist and Master's exchange.

4How will a person be recovered after a fall or equipment failure?

Explain the immediate alarm, fall protection or flotation, retrieval method, medical response and alternative access.

5What changed since the last use?

Check rigging, certification, repairs, berth geometry, weather and vessel condition rather than copying the previous assessment.

Where an observation may arise

PLAN GAP

The assessment did not address pilot-ladder length, combination arrangement, ship-side doors, lee, speed, freeboard, rigging, supervision and communications.

EQUIPMENT DEFECT

Inspection identified damaged step or rope, deck fittings used as unverified strong points, magnet misuse, poor lighting or unattended ladder.

NO SUPERVISION

The arrangement lacked a responsible officer, competent attendant or continuous monitoring.

LIMIT EXCEEDED

Operation continued beyond a weather, movement, angle, freeboard or maker limit.

RESCUE GAP

No effective recovery method was immediately available.

RECORD CONFLICT

Physical condition or configuration did not agree with pilot-ladder inspection log, certificate, rigging checklist and Master's exchange.

Master's practical note

Assess the arrangement as a moving system, not a static appliance. Vessel movement, changing tide and the interface with shore usually determine whether a compliant arrangement remains safe.

Questions reported during inspections

Anonymised user reports, not official OCIMF questions or a prediction of what an inspector will ask.

HumanReported inspection question

The Operator's procedures required the Permit for Aloft and Outboard work permit to be complied when setting up a combination ladder to pick up the pilot. A review of vessel records revealed samewas not complied during pilot boarding at inward transit.

Oil tanker · Deck · Main deck / manifold · February 2026

Equipment boundary and references

Equipment boundary: Follow SOLAS, flag, port, terminal and maker requirements. Stop the operation if a safe arrangement cannot be maintained, even if commercial delay results.

References

  • OCIMF SIRE 2.0 Question Library Part 1, Version 1.0, Question 5.10.1
  • SOLAS Chapter V regulation 23
  • IMO resolution A.1045(27) as amended