Planning LNG and low-flashpoint-fuel bunkering
What is being checked
The inspector is checking whether a low-flashpoint-fuel transfer is supported by compatibility assessment, simultaneous-operations control, exclusion zones, purging, gas detection, ESD testing and trained personnel.
Ready onboard
0/7 completePractice questions
Answer aloud, then open the preparation point.
1What determines the safety zone?
Use the approved bunkering study, transfer conditions, dispersion or risk assessment and local authority requirements.
2Why are lines cooled down gradually?
Controlled cool-down limits thermal stress, vapour generation and pressure shock in cryogenic equipment.
3How is trapped LNG removed before disconnection?
Follow the approved drain, depressurise, purge and gas-free sequence to the designated safe system.
4Which simultaneous operations are prohibited?
State the vessel and port-specific decision from the SIMOPS assessment, not a universal list.
5What stops the operation before ESD is needed?
Monitor weather, mooring, pressure, temperature, gas detection, communication and exclusion-zone integrity against agreed stop criteria.
Where an observation may arise
Hose, manifold, ESD or operating limits are not formally matched.
Concurrent work introduces ignition, access or emergency-response conflict.
Lines are disconnected without safe drain, depressurisation and atmosphere control.
Unauthorised persons or ignition sources enter the controlled area.
Transfer continues outside agreed wind, lightning or movement limits.
Assigned personnel lack required qualification or ship-specific knowledge.
Master's practical note
Examine the transition stages before first flow and before disconnection. Most controls focus on steady transfer, while cool-down, purging and trapped liquid create the more complex changes of state.
Equipment boundary and references
Equipment boundary: This applies only to scoped vessels using LNG or another low-flashpoint fuel. The exact process must follow the fuel type, approved IGF arrangement, port approval and supplier interface.
References
- OCIMF SIRE 2.0 Question Library Part 2, Version 1.0, Question 10.6.3
- IGF Code
- STCW Convention regulation V/3
- ISO 20519
- SGMF LNG bunkering guidance
Last reviewed: 2026-09-10