Airlock ventilation and alarms

RISQ 7D.12Section 7D · Fuel Management (Alternative Fuel: Ammonia)Source marking: V

Applicability: Section 7D applies where equipment, machinery or a system on board uses ammonia fuel. Apply the vessel-specific conditions in this entry.

What is being checked

Airlock pressure and door alarms function and are tested.

Ready on board

0 / 4 checked

Check the vessel’s actual procedures, equipment and records against these points from RISQ 3.2.

Practice questions

Preparation prompts derived from this entry, not an official inspector interview script.

1Is a local door alarm the only alarm required here?

No. The source also calls for manned-location warnings of pressure loss and door opening with lost pressure.

Where a finding may arise

Missing evidence or defects inconsistent with the checks above may prevent a satisfactory answer. These are preparation concerns derived from the question, not explicit additional finding criteria or reported past observations.

Past observations for practice

Anonymised reports, manually reviewed before publication. These are reported experiences, not additional inspection requirements.

No reviewed observations have been added for this entry.

Share an observation for private review

Remove vessel, company and inspector names, report numbers, exact dates and confidential information. Do not paste a complete inspection report.

References and source status

RightShip Inspection Ship Questionnaire, November 2025, version 3.2. Section 7D, page 107, reference 7.12.

The explanation, checklist and practice answer derive from the supplied questionnaire. Reported observations are separately contributed and manually reviewed; they are not official RISQ guidance.

Independent DeepDraft preparation guide, based on the supplied RISQ 3.2 questionnaire. Not an official RightShip product or inspection report.